Completion activities

asked Apr 21, 2015 in Engineering by GerritMcLane (870 points)
What are the usual Completion activities before commissioning of a facility or unit?

1 Answer

0 votes
answered Apr 21, 2015 by bxander (1,180 points)

Here are some activities that should take place during completion but not limited to:

  • Dimensional checks where required
  • Motors / pumps compressors pre-alignment checks & Hot alignment
  • Flushing and hydro-testing
  • Piping re-instatement & bolt tightening checks
  • Nitrogen/Helium leak testing
  • Oil flushing
  • Cooling & heating medium flushing
  • Cold loop checking
  • Hot loop checking
  • Valve timing checks (Safety & Control valves)
  • PSV Calibration Checks
  • Cause & Effect testing
  • Motor running check
  • Testing of large drives
  • Running of electric generators
  • Rotating equipment test
  • Generator and UPS Load test
  • Electrical Ex Checks
  • Preservation

Related questions

1 answer
asked Apr 7, 2015 in Engineering by wangroc (3,280 points)
2 answers
asked Apr 20, 2015 in Engineering by guyredumis (540 points)
2 answers
asked Apr 10, 2015 in Engineering by belmoreno (2,190 points)
...