Should FPSO Contractor be invited along with Subcontractors to a pre-installation survey?

asked May 31, 2014 in Operations by pasmith (3,320 points)
Should FPSO Contractor be invited along with Subcontractors to a pre-installation survey carried out at the field to confirm agreement for offshore activities to proceed?

1 Answer

0 votes
answered May 31, 2014 by gagonza (3,020 points)
Yes, all Contractor and Subcontractors should be invited to the pre-installation survey carried out at the field for a visit typically 3-days to witness and confirm agreement for offshore activities.
...