Is FPSO Contractor required to install appurtenances during Offshore Installation and Commissioning?

asked Jun 1, 2014 in Installation by pasmith (3,320 points)
Is FPSO Contractor required to install appurtenances to enable FPSO operation including deep well caissons, offloading hoses, etc. during Offshore Installation and Commissioning?

1 Answer

0 votes
answered Jun 1, 2014 by gagonza (3,020 points)
FPSO Contractor typically proposes only offshore installation of the seawater lift hoses. All other FPSO appurtencances will be preā€installed onshore.
...